The world’s biggest intranet, the Navy-Marine Corps Intranet (NMCI, with a total price tag of about $10-billion) serves more than 500,000 users – mostly marines and sailors in the field.

 

The end users are happy with the intranet – whether its dependability, support, or the ability to find information – user satisfaction is about 70%. Mission accomplished. Or is it…

 

NMCI is viewed as a failing project. A report by the Government Accountability Office (see GAO-07-51) is critical of NMCI for never implementing a plan developed in 2000 to measure and report project progress. GAO says that NMCI intranet has met a paltry three of 20 performance targets set for the intranet.

 

 

"By not implementing its performance plan, the Navy has invested, and risks continuing to invest heavily, in a program that is not subject to effective performance management and has yet to produce expected results," auditors said.

 

But the real damning evidence is from management. In two different satisfaction surveys with naval and marine commanders, the intranet was shot to pieces.

 

“Specifically, on a scale of 0-3 with 0 being not satisfied, and 1 being slightly satisfied with the contractor’s support in meeting the mission needs and strategic goals of these organizations, the average response from all organizations was 0.65 and 0.76 in September 2005 and March 2006, respectively. The latest survey results show minor differences in the degree of dissatisfaction with the four types of contractor services addressed (cutover services, technical solutions, service delivery, and warfighter support),” says the GAO report.

 

Users can find information and do most of the things that they want, but the intranet is failing to live up to its purpose. If an intranet fails to achieve business objectives and deliver on the priorities of management, then the intranet fails. It’s money wasted, and opportunity squandered.

 

Design and usability are important, but both are tertiary values compared to planning, performance and content (including governance, process and resources). Despite the incredible hype and emphasis on look-and-feel and usability testing (specifically these ridiculous awards reports and ceremonies), colors, pictures, blogs, and podcasts are all for nothing if the intranet does not have well executed plan that supports management objectives.

 

 